1,671m² at St David's Shopping Centre. Access restrictions meant mixing Isocrete Ultimate K Screed on site in a 3-phase forced-action mixer with bulk-bag sand, delivered alongside two other Uniqlo stores at the same time.
Summary: CSC Screeding supplied and laid 1,671m² of Isocrete Ultimate K Screed for Uniqlo at St David's Shopping Centre, Cardiff. The concrete was mechanically prepared and bonded with Isocrete Polymer 70. Because of access restrictions, the screed was mixed on site in a 3-phase forced-action mixer using bulk-bag sand. Three Uniqlo stores were delivered simultaneously.
CSC Screeding supplied and laid 1,671m² of screed for the Uniqlo store at St David's Shopping Centre, Cardiff. It was one of three Uniqlo stores we screeded simultaneously, alongside Churchill Square, Brighton and Canary Wharf, London, with each store getting the screed system that suited its site.
A retail unit inside St David's Shopping Centre, where access restrictions shaped how the screed could be mixed and delivered. This store was also running at the same time as two other Uniqlo stores in Brighton and London.
The primer and bonding grout Flowcrete specifies for bonding Isocrete K-Screeds to a prepared concrete base.
Source: Flowcrete Ultimate K-Screed technical data sheet
An early drying, rapid strength, semi-dry cementitious screed. Flowcrete states a 24-hour walk-on, 3-day drying time and over 40N/mm² compressive strength.
Source: Flowcrete product page: flowcrete.eu, Isocrete Ultimate K Screed
Descriptions and figures are from the manufacturers' published information. Performance depends on specification and site conditions.
Isocrete Ultimate K Screed, bonded to mechanically prepared concrete with Isocrete Polymer 70.
Access restrictions meant the screed was mixed on site in a 3-phase forced-action mixer using bulk-bag sand.
1,671m² at St David's Shopping Centre, Cardiff.
Yes. Cardiff was one of three Uniqlo stores CSC screeded simultaneously, alongside Brighton and Canary Wharf in London.