Last minute change to screeding plan
March 2012
Many a time we have spoken to clients about the advantages of site mix over liquid screeds. Here is a very good example of flexibility from a recent project.
The client wished to save time on some tiling work. Certain areas needed to be raised by 15mm. He had two choices. First option, post screeding, was somehow to find a way to build up parts of the floor using levelling products or carpentry. Alternatively he could use the second option of asking his floor screeding contractor for assistance.
A quick discussion on site, a verification of the floor plans and it was agreed that CSC could do the job.

Image shows where the screed needs to be raised

Check the plans

Start the screeding, check the levels

Raised area can be seen to progress

Raised area near completion

Raised area seen from another angle
So there you have it. To accommodate this late customer request with a liquid floor screeding solution would have been quite difficult.
.