Screeding for interior fit-outs
For retail fit-out contractors and Tier 1 main contractors delivering store fit-outs. We plan the floor back from the store-opening date, so the shopfitters get a level, tested floor when the programme says they will.
Mainly across the South East and East of England, and nationally for high-value retail fit-out.
Established in 1987. Over 3,000 projects since 2010.
Programme certainty against the opening date
On a store fit-out the opening date does not move. The floor sits between strip-out and the shopfitters, so if it is late, out of level or still wet, every trade after it waits. We plan the floor so it is ready when the programme says it will be.
Planned back from the opening date
We start from the date the shopfitters need the floor and work back: preparation, pour, drying and testing, each with a date.
Scope agreed before we price
We review the drawings, the specification and the existing slab first, so the floor build-up is settled before it reaches the programme.
No storage needed
The Maverick batches flowing screed on the truck. It needs a pit lane, such as a loading bay, not a compound.
Output when the window is short
Up to 1,000m² a day, depending on site, access and specification, so a short floor window can still be met.
Tested before the finishes
The floor is moisture tested to the flooring manufacturer’s method before the finish goes down, not judged by the calendar.
Records for your handover file
Test records and certificates are supplied with the floor, so your package manager has the evidence at handover.
Named proof: Lidl Caterham, 3 weeks cut to 5 days
A Lidl store fit-out on a busy high street in Caterham, Surrey, for the fit-out contractor Forum Contracts. Around 2,000m² of floor to screed, and nowhere outside to store materials.
The specified sand and cement screed would have meant daily deliveries, bulk bags of sand carried into the building and screed mixed inside in pan mixers: a 3-week screed programme. Because of the logistics, the specification was changed to flowing screed.
The Maverick pulled into a loading bay on the high street, batched the screed on the truck and pumped it straight into the store. No materials stored outside, no bulk bags carried in and no mixing inside the building.
Result: the screed programme was cut from 3 weeks to 5 days, and Forum Contracts got the floor back ready for the next trades.
How the screed gets into the store
We use traditional screed pumps and Maverick automated screed trucks. The right method depends on the unit, the access, the specification and the programme.
Traditional screed pumps. We still use conventional pump trucks for traditional sand cement and flowing screed where they suit the site. Pump access is planned with you before the pour, not left to the day.
Maverick automated screed trucks. The Maverick batches flowing screed fresh on the truck and pumps it into the building. It parks at the kerb, a loading bay or the site gate, so a unit with no storage and no compound can still be screeded. More about the Maverick.
Built for retail fit-out contractors and Tier 1 main contractors
This page is for the contractors who deliver store fit-outs: specialist retail fit-out contractors, and Tier 1 main contractors running a store fit-out package. Mainly across the South East and East of England, and nationally for high-value retail fit-out.
Established in 1987. Over 3,000 projects since 2010. Check our accreditations and certificates, see how we work with main contractors, or browse our work.
Choosing a floor contractor for a store programme? Use our 15-point checklist on us, and read why screed jobs go wrong before you sign off the floor package.